| Hamina | Google data-centre campus, Summa (registry: Palvelinkeskus Hamina) | Google (registry project company: Tuike Finland Oy) | Operating — expansion announced (Google, 9 September 2026) | Google plans at least 13 billion € in Finland in 2027–2028 across Hamina, Kajaani, Muhos and Vaala (Google, 9 September 2026). Timing and size of the Hamina works: not published as of 25 September 2026. | Expansion on a live campus: shell trades at the start of each new building, then the long mechanical and electrical phase (electricians, busbar and MV/HV fitters, pipefitters, pipe welders, HVAC, sprinkler, insulation, BMS) and commissioning. Dates not published. | No Gene-Works housing in Kymenlaakso; accommodation is arranged per assignment. | Summa area, Hamina (registry location). Own transport to site is arranged by Gene-Works. |
| Kajaani | Google data-centre area, Otanmäki–Alussuo (registry: Palvelinkeskus Kajaani-Otanmäki) | Google (registry project company: Tuike Finland Oy) | Preparatory works — permits pending (registry, 23 September 2026; Lupa- ja valvontavirasto, 18 September 2026: the detailed plan is appealed, a building ban applies, the EIA is still in progress) | Main construction 2027–2028 under Google's two-year programme (Google, 9 September 2026). Site headcount and peak year: not published. | Greenfield site: shell trades first (steel fixers, precast and steel erectors, roofers/fall protection, crane and lifting) — start depends on permits; then the long mechanical and electrical phase (electricians, busbar, MV/HV, pipefitters, pipe welders, HVAC, sprinkler, insulation, BMS); commissioning towards the end. | Accommodation available nearby through Gene-Works (Kajaani area). | Otanmäki, Kajaani (registry location). Own transport to site is arranged by Gene-Works. |
| Muhos | Google data-centre area, Pyhänselkä / Leppiniemi — 571 ha, 9 buildings in the EIA programme (ymparisto.fi, 16 September 2025; registry: Palvelinkeskus Muhos) | Google (registry project company: Tuike Finland Oy) | EIA in progress — preparatory works (registry, 23 September 2026) | Main construction 2027–2028 under Google's two-year programme (Google, 9 September 2026). "Over 2,000 construction workers" is an estimate quoted by Yle on 10 September 2026 — not a confirmed figure. The municipality is working towards 1,000 new beds for construction workers and holds a business event on 8 October 2026, 17:00–19:00 (muhos.fi, 21 September 2026). | Greenfield, nine buildings: shell trades (steel fixers, precast and steel erectors, roofers/fall protection, scaffolders, crane and lifting) from the permit date; then the long mechanical and electrical phase (electricians, busbar, MV/HV, pipefitters, pipe welders, HVAC, sprinkler, insulation, BMS, standby power); commissioning building by building. | Accommodation available nearby through Gene-Works; the municipality is expanding worker accommodation (muhos.fi, 21 September 2026). | Leppiniemi / Pyhänselkä, Muhos, Oulu region (registry location). Own transport to site is arranged by Gene-Works. |
| Vaala | Data-centre area, Nuojua–Järvikylä (registry: Vaalan datakeskus) | Google named Vaala in its 9 September 2026 announcement and the municipality reported Google's land purchase (vaala.fi); the registry lists the Nuojua–Järvikylä EIA under a different applicant (Erikoissijoitusrahasto UB Uusiutuva Energia) — the relationship between the two is not confirmed. | EIA in progress (registry, 23 September 2026) | Main construction 2027–2028 under Google's two-year programme (Google, 9 September 2026); the Vaala schedule and size are not published. | Not before permits: shell trades first, then the mechanical and electrical phase (electricians, pipefitters, pipe welders, HVAC, sprinkler, BMS) and commissioning. | Accommodation available nearby through Gene-Works (Kajaani area). | Nuojua–Järvikylä, Vaala (registry location). Own transport to site is arranged by Gene-Works. |
| Kirkkonummi | Microsoft data centre, Kolabacken / Sundsberg (registry: Kirkkonummen datakeskus); site works under way since 2025 (kirkkonummi.fi, 27 June 2025) | Microsoft (registry project company: Microsoft 3465 Finland Oy) | Under construction (registry, 23 September 2026) | Phase 1 finishing around the turn of 2026–2027; phase 2 starting in 2026 (Microsoft, April 2026) — phases overlap, which keeps demand for trades continuous. Headcount on site: not published. | Phase 1 building: mechanical and electrical works now and into 2027 (electricians, busbar, pipefitters, pipe welders, HVAC, sprinkler, insulation, BMS, standby power), commissioning expected from 2027. Phase 2 building: shell trades (steel fixers, precast, roofers/fall protection, crane) from 2026. | Helsinki region; no Gene-Works housing here — accommodation is arranged per assignment. | Sundsberg, eastern Kirkkonummi, in the Helsinki commuter area (kirkkonummi.fi). Own transport to site is arranged by Gene-Works. |
| Espoo | Microsoft data-centre area, Hepokorpi (registry: Espoon datakeskusalue) | Microsoft (registry project company: Microsoft 3465 Finland Oy) | Under construction — second building since May 2026 (Microsoft construction update, May 2026) | About 3,500 people working on the project, peak about 7,500 (Microsoft project page, September 2026). Phase 1 finishing around the turn of 2026–2027, phase 2 starting in 2026 (Microsoft, April 2026). | Two buildings at different stages: shell trades (steel fixers, precast, steel erectors, roofers/fall protection, crane) on the second building; mechanical and electrical works (electricians, busbar, pipefitters, pipe welders, HVAC, sprinkler, insulation, BMS) on the first; commissioning of the first expected from 2027. | Helsinki region; no Gene-Works housing here — accommodation is arranged per assignment. | Hepokuja 2, 02940 Espoo (Microsoft, May 2026); Helsinki region. Own transport to site is arranged by Gene-Works. |
| Vihti | Microsoft data centre, Huhmari (registry: Vihdin datakeskus) | Microsoft (registry project company: Microsoft 3465 Finland Oy) | Under construction (registry, 23 September 2026) | Phase 1 to finish December 2026; phase 2 from 2026 (Microsoft, April 2026). Headcount on site: not published by the owner. | Phase 1 building: mechanical and electrical works through 2026 (electricians, busbar, pipefitters, pipe welders, HVAC, sprinkler, insulation, BMS), commissioning from late 2026 / 2027. Phase 2 building: shell trades from 2026 (steel fixers, precast, roofers/fall protection, crane). | Helsinki region (Nummela side); no Gene-Works housing here — accommodation is arranged per assignment. | Hankasalontie 12, 03150 Huhmari, Vihti (vihti.fi, 26 June 2024). Own transport to site is arranged by Gene-Works. |
| Kajaani | LUMI-AI data centre, Renforsin Ranta (conversion of a former paper-machine hall) | CSC – IT Center for Science Ltd | Under construction (registry, 23 September 2026) | A small site by data-centre standards; about half of the building-services workforce comes from Kainuu (press release, 3 September 2026). Commissioning planned for 2027. | Conversion, so mostly building services — electricians, pipefitters, pipe welders, HVAC, sprinkler, insulation, BMS — through 2026–2027; commissioning in 2027. | Accommodation available nearby through Gene-Works (Kajaani area). | Renforsin Ranta business park, Kajaani (registry location). Own transport to site is arranged by Gene-Works. |
| Kajaani | XTX Markets data centre, Tihisenniemi | XTX Markets Oy | Under construction (registry, 23 September 2026) | Schedule and headcount: not published as of 25 September 2026. | Greenfield: shell trades first (steel fixers, precast, steel erectors, roofers/fall protection, crane); mechanical and electrical phase to follow (electricians, MV/HV, pipefitters, pipe welders, HVAC, sprinkler, BMS); then commissioning. | Accommodation available nearby through Gene-Works (Kajaani area). | Tihisenniemi, Kajaani (registry location). Own transport to site is arranged by Gene-Works. |
| Mäntsälä | Verne data-centre campus, Kapuli business area (second site: Nebius Mäntsälä 2, permitting) | Verne (under construction); Nebius (Mäntsälä 2, permitting) | Under construction (registry, 23 September 2026) | Schedule and headcount: not published as of 25 September 2026. | Verne: shell trades first, then the mechanical and electrical phase (electricians, busbar, pipefitters, pipe welders, HVAC, sprinkler, standby power, BMS) and commissioning. Nebius 2: after permits. | North of the Helsinki region; no Gene-Works housing here — accommodation is arranged per assignment. | Kapuli business area, Mäntsälä (registry location). Own transport to site is arranged by Gene-Works. |
| Kouvola | atNorth FIN04, Myllykoski (further Hyperco and Nova Complex sites in Kouvola) | atNorth (FIN04); Hyperco Data Systems Oy and Nova Complex (other Kouvola sites) | Under construction (registry, 23 September 2026) | Schedule and headcount: not published as of 25 September 2026. | Shell trades first (steel fixers, precast, steel erectors, roofers/fall protection, crane); mechanical and electrical phase (electricians, MV/HV, pipefitters, pipe welders, HVAC, sprinkler, standby power, BMS); then commissioning. | No Gene-Works housing in Kymenlaakso; accommodation is arranged per assignment. | Myllykoski industrial area, Kouvola (registry location). Own transport to site is arranged by Gene-Works. |
| Lappeenranta | Nebius AI data centre, Pajarila (registry: Pajarilan datakeskus) | Nebius | Under construction (registry, 23 September 2026) | Schedule and headcount: not published as of 25 September 2026. | Shell trades first; mechanical and electrical phase (electricians, MV/HV, pipefitters, pipe welders, HVAC, sprinkler, standby power, BMS); then commissioning. | No Gene-Works housing in Etelä-Karjala; accommodation is arranged per assignment. | Pajarila, Lappeenranta (registry location). Own transport to site is arranged by Gene-Works. |